29.04.2017 DEMOLITION WORKS QUAYS OF THE SCHELDT


On Saturday 29th of April we successfully executed the demolition works of the quay walls in Antwerp City Centre by order of Waterwegen en Zeekanaal. The quay wall was demolished over a length of 123m using demolition charges. This was done through a carefully planned demolition plan which reduced the impact of noise and vibration to the surrounding area, as well as ensuring the safety of the demolition team and local community. Herbosch-Kiere are scheduled to carry out further demolition works at the end of May, after which we will start rebuilding the new quay wall.