Project

ENVIRONMENTAL WORKS - Removal asbestos

Removal of asbestos

Phase 1: remediation and asbestos removal from backfill on private land in Kapelle-op-den-Bos.  The main work involved removing ± 38,000 t of asbestos waste from ± 400 different plots of land. All plots had to be restored to their original state.

Phase 2: Remediation and asbestos removal from private and public land.

The main work involved removing ± 20.000 t of asbestos waste from ± 166 different plots of land. All plots had to be restored to their original state.

Constructor(s): 
Herbosch-Kiere
Developer: 
OVAM
Project duration: 
01-04-2007 - 28-11-2012