Saint-Nazaire is France’s first offshore wind farm.
In order to install two high-voltage cables at the Saint-Nazaire wind farm, Herbosch-Kiere dredged and then backfilled a trench of approximately 750 metres in the shallow tidal zone near the beach at La Courance. We also helped our partner ETMF (Eiffage Travaux Maritimes et Fluviaux) sink and install a double HDPE pipe.
We used our barge GAVERLAND for these works which is equipped with our Hitachi ZX870 and Hitachi ZX470 cranes.