Herbosch-Kiere was responsible for replacing the slope and the area surrounding the RYCO building (Royal Yacht Club Ostend).
We built a new access and work jetty and a slipway. We also made part of the marina deeper and removed and installed tubular piles. We also installed new foundations underneath the club building using ground anchors and micro-piles. Sheet piles were driven in around the existing building and anchored using 85 final ground anchors. The foundations of the existing building were strengthened using 83 micro-piles which were installed using a small drilling machine from inside the building.